«Back |
|
879 Requirements |
|
|
|
879 Processing Requirements |
|
824 Application Advise price change status
messages |
Initial Contact -
please contact the Business/Operational contact or buyer
before you begin price changes. Select a division that you currently
do business with to begin testing.
Vendor will contact the party listed
in the 879 contact listing for startup of Price Changes.
Exchange of the partner information
Verification of Kroger Duns and suffix numbers for price changes:
-
Verification of the EDI Price Change Mapping.
-
Test Phase -
during this time the Kroger division will review all price changes sent EDI for
accuracy.
-
The
Business/Operational contact or buyer will be responsible for the following:
-
Reviewing the Manufacturer Price Listing and establishing
any needed brackets in the On-Line Purchasing System
-
Exchange item upc information by use of the manufacturer's
price sheet
-
Establish the procedures for testing with the vendor and in
addition to setting the (T) flag in the On-Line Purchasing
System
-
The
Business/Operational contact or buyer and vendor will discuss and agree on all
business issues prior to start up.
-
The
vendor will send a test transmission to the production
mailbox.
-
The
Business/Operational contact or buyer will verify that the transactions was
received, and communicate any problems back to the
vendor.
-
Parallel Phase
-
The vendor will send all
future Price Changes via EDI and continue to submit the hard copy Kroger form
(if requested by the Kroger Operation Unit).
-
The Business/Operational contact
or buyer will verify the EDI transaction against the hard copy Kroger form. Discrepancies
will be reported from the Business/Operational contact or buyer to the vendor.
-
Production Phase
-
The
Business/Operational contact or buyer will make the decision to go into the
production phase, thus eliminating the hard copy form and
sending the data to the production mailbox. The
Business/Operational contact or buyer at the Division will change the flag to (P) in the
On-Line Purchase System.
-
Kroger
will require a 30 day lead time for all price changes.
879 Data Requirements
|
-
Data
must conform to the EDI standard Kroger's current version is
004010 in both the UCS and X12 Standards.
-
The
EDI Price Change must match the hard copy Price Notification.
UPC's, dates, brackets and list costs, bracket minimum
quantities, price protection, and allocation must all match.
-
The
Manufacturer Price List must be submitted (30) days in advance
of the EDI transmitted 879 to allow ample time for the price
brackets to be set up by the buyer in the purchasing system.
There is also a flag that must be turned on in the purchasing
system to accept EDI price changes.
-
The
EDI Price Change must be transmitted ten (10) days prior to
the first order date (G6201 = 87).
-
Price
brackets must apply to all items for that particular vendor.
-
The
price brackets must be a common delimiter (cs, lbs, ea), you
can not mix brackets within the 879.
-
A
vendor should send no more than (10) brackets. Our
purchasing system only allows for 4 brackets, so the buyer
must enter into his/her purchase system the 4 brackets that
will normally apply.
-
Data
Assumptions.
-
All
price changes received are unique and new
-
Kroger can not handle changes or deletions through EDI.
-
All
UPC's within the price change are unique.
-
If
the price change contains two (2) or more UPC's with the
same number, then the program will use the last UPC, and
ignore the previous ones.
-
There
is a limit of 250 items that can be sent on a price change.
824 Application Advise |
-
Kroger
is now sending 824-879 Price Change Status notices. Our goal
is for you, our Trading Partners, to use the 824 to take
action quickly on rejected price change information sent to
you by Kroger.
Kroger does not intend to do any follow up with Trading
Partners receiving an 824 on rejected 879-price changes. The
824 will be Kroger’s notification to your company there was a
problem.
-
Kroger
requires each EDI Trading Partner sending 879's to have
their
EDI system set up to accept and use an 824 Application Advise.
-
Please
review documentation "879 Problem Support" for the specific
error messages and explanation of the cause on this site.
-
Please
contact your Business/Operational contact or buyer for
questions/verifications.
-
EDI
questions can be directed to the Kroger EDI TEAM via E-Mail:
edi@kroger.com